%[This is not official and for distribution, as we still have to discuss with TRIUMF management.]
|
||||
|
||||
An initial test run for measuring protons emitted from Al targets was performed by a subset of this collaboration
|
||||
at PSI in 2009. It helped to commission part of the apparatus used for the current proposal. It also showed
|
||||
deficiencies which helped to define and optimize the set-up proposed here. In particular, the beam
|
||||
quality, the X-ray detection, the thin dE/dx detectors, the shielding of stray muons etc. need additional
|
||||
careful attention.
|
||||
|
||||
In 2012, a joint COMET/Mu2e project on charged particle emission was started, when the high relevance of
|
||||
proton emission for the new COMET Phase-I idea was realized. Due to the geographical advantage of
|
||||
Vancouver, as a good crossing point for the Fermilab and J-PARC collaboration, a proposal~\cite{triumf12}
|
||||
was submitted to TRIUMF in summer 2012, and accepted with high priority. The PAC recommendation reads:\\
|
||||
{\it\bf ``The proposed set of muon capture background measurements are deemed crucial to the design and understanding of future neutrino-less muon-to-electron decay experiments, such as COMET and mu2e. Thus the committee approves this proposal with high scientific priority.
|
||||
It is noted that it is not yet clear which muon beamline will be available for this study with the desired negative muon properties.
|
||||
Once a suitable beamline has been identified that will be ready and available on the required timescales, the committee recommends that the full 36 shifts be granted.''}
|
||||
|
||||
Unfortunately, the above-mentioned availability of a suitable beamline for low energy $\mu^-$ turned out to be a problem.
|
||||
The allocated test beam times in fall of 2012 could not be realized, as the M9B beamline experienced vacuum problems
|
||||
at the T2 target station as well as difficulties with the superconducting decay channel. Moreover, TRIUMF cloud beamlines
|
||||
with better momentum bin essential for this experiment, are not foreseen to be operated with negative muons.
|
||||
In this situation, the collaboration asked the TRIUMF management to put S1371 on standby.
|
||||
|
||||
Meanwhile, PSI built a new low energy muon beam for particle physics, initially for the MuSun experiment. This
|
||||
beamline was successfully commissioned by the MuSun collaboration, including some members of the present
|
||||
collaboration. The results were extremely positive. In particular, the beamline appears to be the world-wide
|
||||
superior channel for experiments needing muon beam \textit{at low energies with very narrow energy spread}.
|
||||
This advantage is due to the high proton intensity at PSI, combined with a special cloud muon channel,
|
||||
which selects the momentum with three bending magnets and thus allows for a dispersive focus.
|
||||
The initial commissioning results by the MuSun collaboration promise excellent conditions for the thin
|
||||
targets anticipated in AlCap. Further beam details are discussed in the MuSun progress report, submitted to this BVR.
|
||||
|
||||